Case Study - Catch Basin
Client
Cherry Point Naval Air Station, NC
Project
Catch Basin Rehabilitation
Location
Cherry Point, NC
Description
Box structures were deteriorated and needed channels built to better direct the flow.
Solution
JCB Construction was contracted to line 49 stormwater catch basins in year 2000. Each of the structures were configured differently
and uniquely shaped. The field measurement on the below is a sample of the configuration. The Poly-Triplex Liner was custom fabricated
to fit each structure. Channels were formed to improve flow and structures lined preventing further deterioration.
Benefit
The structures are structurally sound and improved flow has been achieved.
Photos
This is an example of a typical configuration of the structures lined. Poly-Triplex Technologies, Inc. manufactured custom
liners to fit the catch basins. JCB Construction removed the top grate and lowered the liner into the catch basin, then
applied air pressure and steam heat to cured the liner in place without any excavation.
Comments
Very pleased with the results, the N.A.S. completed another project in 2007 where they lined an additional 11 structures.
Poly-Triplex provided a more permanent solution than new construction and provided a 10-Year warranty.
|
|